Upgrades at Namsnails
Namsnails oprerate in harsh conditions. Being situated in the Namib desert next to the Swakop River. With that comes unique challenges leading us to be innovative in our approuch to snail production. Within that dynamics, Namsnails embarked on an upgrading process creating full environmental control and introduced a state of the art breeding house and hatchery.
Upgrade timeline and opening of new production season
June 2025 - December 2025
October 2024 - January 2025
February 2025 -
March,5 2025 -
Upgrade of growing house with full climate control including temperature, humidity and wind.
Construction of an all new Breeding house and hatchery to produce 2 million eggs per cycle.
Introduction of breeder snails to the breeding houses and the production of the first juveniles for placement in production houses in March 2025.
Introduce first 100 000 juveniles to the growing houses. Millions to go!